Back To Factory Reset: ECG Announces 22-Day ‘Dumsor’ Schedule For Accra; 71 Communities To Be Affected

The Electricity Company of Ghana (ECG), has announced that parts of Accra will experience scheduled power outages for 22-days starting from Monday, June 28, 2021.

According to the power distributor, the outages would allow the Ghana Grid Company (GRIDCo) to complete the last phase of repair works on some bulk supply points and transmission cables in Accra.

The last phase of the repair and upgrade works, which begins on Monday, June 28, 2021, will see an upgrade in the Volta-Achimota-Mallam transmission lines.

READ ALSO:  Ghanaians Hail Sarkodie After He Shared A GoFund Me Account Of A Young Boy

The exercise will cause an interruption in power supply to some 71 communities within Accra.

The communities have been categorized into 6 groups, each of which will be without power from 6:00 pm to 12:00am once a week, within the 22-day period lasting between June 28 and July 19, 2021.

READ ALSO:  Afia Schwarzenegger's Father Is Dead

The Managing Director of ECG, Mr. Kwame Agyeman-Budu has said:

We have plans to start outages so that GRIDCo can continue the upgrading… We want to notify the public that there is going to be some outages starting each day 6pm to 12midnight, and we’ll do our best to minimize the outages, but we want them to be informed that they should expect some outages within that period.

READ ALSO:  Yvonne Nelson Launches #Dumsormuststop Campaign

We’ve spoken to GRIDCO to speed up the work. In all, we are taking 22 days to complete the lines, so hopefully by the end of the 22nd day.

Source: Ghbase.com

Source: Kingaziz.com